prima:No resolution in sight for conflict between Genera PR and the Public-Private Partnerships Authority over temporary generation bidding expenses

Although no final agreement has been reached, the costs of the process, as of December, were approaching $400,000

April 1, 2026 - 4:47 PM

Although the 3PPO, chaired by Osvaldo Carlo Linares, has reached preliminary agreements with the companies Power Expectations and Gothams Energy, the FOMB has slowed their final approval with extensive information requirements. (Ramon "Tonito" Zayas)

Genera PR and the Puerto Rico Public-Private Partnerships Authority (P3A) are in dispute over who will bear the administrative costs of the procedure to acquire 800 megawatts (MW) of temporary generation, a request for proposals (RFP) that was issued over a year ago without, to date, a single contract materializing.